Injection moulding cost is mostly the tool, divided by how many parts you make, plus a small per-part cost for resin and machine time. On a few hundred parts the mould can be most of the price; on tens of thousands it shrinks to cents and the cycle time takes over. To estimate a price, cost the tool, the cycle, the resin and the setup separately, then spread the fixed parts over the batch.

Key points

  • Four things set the price: the tool, the cycle time, the resin per shot and the setup per run.
  • The tool is a fixed cost. Divide it by the parts it will make and you have its share of each unit price.
  • Cycle time is set mostly by cooling, and cooling is set mostly by the thickest wall.
  • More cavities cost more up front and less per part. Long runs justify them; short runs rarely do.
  • Design changes after the tool is cut are expensive, so design for the mould before you order it.

What is injection moulding, and why is the price shaped like this?

Injection moulding (injection molding in the US) forces molten plastic into a steel or aluminium mould, holds it under pressure while it cools, then opens the mould and ejects the part. The machine does the same thing every few seconds for as long as you keep feeding it resin.

That is the whole economic story. The mould is designed and machined once, at real cost. After that, each part costs very little. A price for a moulded part is therefore two prices glued together: a large fixed amount for the tooling, and a small variable amount per part. Every decision about whether to mould, and how, comes down to how those two lines trade off.

The technology page for injection moulding covers the process itself. This article is about the arithmetic.

What drives the cost of the mould?

The tool is usually the largest single number on the quote, and it is often shown as a separate NRE (non-recurring engineering) line. What makes it bigger:

DriverWhy it costs more
Tool materialAluminium machines fast and is cheap, but wears out sooner. Hardened steel costs more to cut and lasts far longer
Part sizeA bigger part needs a bigger mould base, more machining and a bigger press
Number of cavitiesEach extra mould cavity is another set of features to machine, polish and balance
UndercutsAn undercut needs a side action, lifter or hand-loaded insert: moving parts inside the tool
Surface finishA high polish or a specified texture adds hours of finishing work to the cavity
TolerancesTight tolerances mean more careful machining, more trial shots and more tool adjustment
Gate and runnerA hot runner system costs more than a cold runner, but wastes less resin per shot

As a rough guide, a simple single-cavity aluminium tool for a small part might cost in the low thousands, while a multi-cavity hardened steel production tool can run to tens of thousands or more. Those are wide ranges on purpose: the only way to know a tool’s price is to have a toolmaker quote the actual part.

Tool life matters as much as tool price. An aluminium tool may be good for thousands to tens of thousands of shots; a hardened steel tool can run hundreds of thousands to a million or more. If you need 200,000 parts, the cheap tool is not cheap: you will buy it several times.

What sets the cycle time?

The cycle time is the time from one mould close to the next. It has four phases: injection, holding, cooling and ejection. Cooling is usually the longest, and it is governed by the thickest wall in the part. Cooling time grows roughly with the square of wall thickness, so a part with a 4 mm section can take far longer to cool than the same part designed at 2 mm.

This is why moulding design guides insist on uniform walls, coring out thick sections and using ribs instead of solid mass. It is not only about sink marks; it is about money per shot.

Per-part machine cost is then simple:

  • Machine cost per shot = press hourly rate × cycle time in hours.
  • Machine cost per part = machine cost per shot ÷ number of cavities.

A bigger press has a higher hourly rate, so part size feeds the price twice: once through the tool, once through the machine.

How do you cost the resin?

Resin is priced by weight. For each shot, take the part weight plus its share of the runner (the channels that feed the cavities), then multiply by the resin price per kilogram. A cold runner is often reground and reused for less demanding parts, but some customers and some materials forbid regrind, so check before you count it as free.

Engineering resins with glass fill, flame retardants or medical grades cost several times more than commodity polypropylene or ABS. For a small part, resin is often a minor line next to the tool. For a large, heavy part in an engineering resin it can be the biggest variable cost.

What about setup and the batch?

Every production run needs the mould hung in the press, heated, purged and dialled in, and the first parts inspected. That is a setup cost charged per run, not per part. It is small next to the tool, but on short runs it still shows up, and it is why moulders often have a minimum run size.

Worked example: amortising a tool across four batch sizes

Worked example: a small ABS housing in a two-cavity aluminium tool. Every figure here is an example for the arithmetic, not a market price.

Inputs: tool €12,000; resin €2.50/kg; 28 g per part including its runner share; 30 s cycle; 2 cavities; press rate €54/h; setup €450 per run, one run per batch.

LineCalculationPer part
Resin0.028 kg × €2.50/kg€0.070
Machine time€54/h × 30 s ÷ 3,600 s/h ÷ 2 cavities€0.225
Variable cost per part€0.070 + €0.225€0.295

Now spread the fixed costs over the batch:

BatchTool shareSetup shareVariableUnit cost
1,000€12,000 ÷ 1,000 = €12.00€450 ÷ 1,000 = €0.45€0.295€12.75
5,000€12,000 ÷ 5,000 = €2.40€450 ÷ 5,000 = €0.09€0.295€2.79
20,000€12,000 ÷ 20,000 = €0.60€450 ÷ 20,000 = €0.02€0.295€0.92
100,000€12,000 ÷ 100,000 = €0.12€450 ÷ 100,000 = €0.0045€0.295€0.42

Check at 5,000 parts: €12,000 + €450 + 5,000 × €0.295 = €13,925, and €13,925 ÷ 5,000 = €2.785, which rounds to €2.79.

Two things stand out. First, the unit cost falls by a factor of about 30 between 1,000 and 100,000 parts, and almost all of that fall is the tool share. Second, below a few thousand parts the tool is nearly the whole price, which is exactly where other processes start to compete. The comparison with 3D printing and the comparison with vacuum casting work through those break-evens.

Should you amortise the tool into the part price?

Tool amortisation means folding the tool into the unit price instead of invoicing it separately. Both approaches are common:

  • Tool invoiced up front. The customer pays for the mould, usually owns it, and then pays a low unit price. Clear, and the moulder carries no risk if the second order never comes.
  • Tool amortised over an agreed quantity. The unit price is higher until that quantity is reached. Easier for the customer’s cash flow, but the moulder carries the risk, so the agreement needs a clause covering what happens if the volume never materialises.

Whichever you choose, write down the quantity the tool is amortised over. It is the number everyone forgets, and it is the one that decides whether the job made money. The same logic of fixed cost per run versus cost per part runs through quantity pricing and batch discounts for every process.

How do you bring the cost down?

  • Design for the tool. Add draft to every face that slides out of the mould, remove undercuts that need side actions, and keep walls uniform. The minimum wall thickness guide has typical ranges for moulded parts.
  • Match the tool to the volume. Do not buy a hardened multi-cavity tool for a 2,000-part pilot, and do not run 500,000 parts from aluminium.
  • Add cavities when the run is long. Doubling the cavities roughly halves machine time per part. It pays back only when the extra tool cost is smaller than the machine time it saves over the tool’s life.
  • Prototype first. A printed or cast part catches design errors before they are cut into steel, where every change means welding, re-machining and re-sampling.

How shops quote moulding today

Moulding quotes are still built mostly by hand, because the tool needs a toolmaker’s eye on the actual part. The variable side, resin per shot, cycle time and setup, is formula work and benefits from the same structured approach as any other process: rates, quantities and a visible price breakdown.

Quotometry gives a budgetary injection moulding estimate from the uploaded file: the tool, from projected area, depth, cavities, side actions and the steel class the buyer picks, and the part, from shot weight and a cycle dominated by cooling. Every moulding line goes to the shop’s review before it is confirmed, because draft is not measured and flow is not simulated; the instant figure tells a buyer early whether moulding fits their volume (see injection moulding).

Questions people ask

Why is injection moulding so expensive for small quantities?

Because the mould is a one-off engineering job that has to be paid for whether you make ten parts or ten thousand. Spread over a small batch, the tool dominates the unit price. Spread over a large one, it almost disappears and the price falls towards resin plus machine time, which is why moulding is cheap only at volume.

Who owns the injection mould once it is paid for?

It depends on the contract, so read it. Commonly the customer pays for the tool as a separate line and owns it, while the moulder stores and maintains it. Some moulders amortise the tool into the part price instead and keep ownership until the agreed quantity is reached. Agree storage, maintenance and transfer terms before the tool is cut.

How can I make an injection moulded part cheaper?

Simplify the tool first: remove undercuts that need side actions, add draft to every face that leaves the mould, keep walls uniform so the part cools quickly, and avoid texture you do not need. Then look at volume: a second cavity costs more up front but halves machine time per part, which pays back on long runs.

What is a typical cycle time for injection moulding?

For small and medium parts, cycles often fall somewhere between about 10 and 60 seconds, but the real number depends on wall thickness, resin and mould cooling. Cooling is usually the longest part of the cycle, and it grows quickly with wall thickness, so a part with thick sections runs slower and costs more per shot.